NFPA 3 & 4 – What’s New?

Issue 91: NFPA 3 & 4 – What’s New?

By Doug Fisher, P.E., FSFPE

NFPA 3,1 Recommended Practice for Commissioning of Fire Protection and Life Safety Systems, and NFPA 4,2 Standard for Integrated Fire Protection and Life Safety System Testing, were both recently approved by the NFPA Standards Council for publication as 2015 editions.  For both documents, this has been a long process, but finally the fire protection community has two separate documents to fill a much needed gap related to fire protection and life safety systems (FP&LSS).

 

 

 

 

Before reviewing what's new with these documents, it is important to talk about how they got to where they are.  The concept for developing an NFPA document on commissioning FP&LSS systems started back in 2005 when the NFPA Standards Council identified the need for more technical information on commissioning FP&LSS.  This resulted in an NFPA document entitled Commissioning Fire Protection Systems.3

 

 

 

Soon thereafter, NIBS submitted a proposal to NFPA requesting that NFPA become involved in FP&LSS commissioning as part of the NIBS total building commissioning project.  An NFPA Technical Committee was formed, and it first met in 2008.  The end result was the 2012 edition of NFPA 3. 

Even before the 2012 edition was published, the committee felt that commissioning and integrated FP&LSS system testing were two distinct events that should be treated separately from an NFPA standards point of view.  The committee began working on the best way to include the functions into separate documents, yet allow them to still work together where needed. 

 

 

 

This allowed the creation of NFPA 3, on commissioning FP&LSS and NFPA 4, which addressed integrated FP&LSS System Testing.  The question that remained was whether each document should be a recommended practice, standard or code.  Since commissioning (Cx) is (currently) more of an owner’s concern, the decision was made to continue to move NFPA 3 forward as a recommended practice.  Integrated FP&LSS testing, however, is an aspect that is not required by any of the installation standards, although it is necessary to be performed in order to verify integrated FP&LSS systems perform as intended.  Because of the nature of integrated FP&LSS system testing, the decision was made to publish NFPA 4 as a standard.

 

Changes to NFPA 3

Before discussing the changes to NFPA 3, it is essential to understand what Cx is and what it is not.  In the fire protection industry, commissioning is often used as a buzzword in reference to acceptance testing of final turnover of the system to the owner.  "We commissioned the sprinkler system” is a common, yet incorrect, phrase.  Commissioning is not acceptance testing, nor is it integrated system testing. 

 

 

Acceptance testing does not equal commissioning; however, commissioning can include acceptance testing.  Paraphrased, commissioning is the process of verifying that systems are designed, installed, functionally tested and capable of being operated and maintained according to the owner’s operational needs.  The key words are "process” and "owner’s operational needs.”  The AHJ is noticeably, and intentionally, missing as NFPA 3 is written for the owner.

 

The 2015 edition of NFPA 3 was not a major revision but, rather, a continuation of the initial efforts to develop concise recommended practices for commissioning.  While there were minor changes throughout the entire document, two major revision items are:

  1. Elimination of all recommendations for integrated system testing.  As can be assumed by the development of NFPA 4, all references to integrated system testing were removed from NFPA 3 (old chapter 7) and moved into NFPA 4.  Throughout the document, the text was tweaked to reference NFPA 4 and how integrated FP&LSS system testing works with Cx.
  2. Clarification and expansion of the recommendations for existing FP&LSS system commissioning, otherwise known as re-commissioning (Re-Cx) and retro-commissioning (Retro-Cx).  The information associated with Re-Cx and Retro-Cx was increased by a factor of four to respond to user requests for clarification on what should be performed during Re-Cx and Retro-Cx.  The definition of Re-Cx was revised to clarify that it only applies to systems that were previously subject to Cx, and its purpose is to verify the system performance continues to meet the owner’s project requirements (OPR) and the basis of design (BOD).  Re-Cx should be performed when specified in the Cx plan, or when a change in the FP&LSS systems affects the operation of such systems.

Specific guidance was then provided to clarify what steps should be included in the Re-Cx process in order to verify that the system performance continues to meet the OPR and BOD.  The definition of Retro-Cx was revised to clarify that it only applies to systems that were not previously subject to Cx.  Retro-Cx should be performed when concerns related to design, installation or operation are identified through the inspection, testing and maintenance process, or when a change in the FP&LSS systems affects the operation of such systems.

 

 

As with Re-Cx, specific guidance was provided to clarify what steps should be included in the Retro-Cx process.  With Retro-Cx, there may not be an OPR or BOD available, so the Cx team is responsible for developing an OPR and BOD based on discussions with the current owner and an historical review of the project.

 

Changes to NFPA 4

Some of the key points of NFPA 4 include:

  1. The standard does not address individual system testing or performance.  This is covered by the individual installation standard.
  2. NFPA 4 provides "how” to perform integrated system testing but not "when.”  The frequency of integrated system testing will be noted in the design documents, Cx plan or applicable codes and standards.  This was such an important topic to the committee that the text was worded to state "this standard shall not be interpreted (emphasis added) to require integrated fire protection and life safety systems testing…”  The committee wanted to make sure there was no confusion about this point.
  3. NFPA 4 establishes the requirement, role and responsibility for an Integrated Test Agent (ITa).  While the owner is responsible to verify that integrated system testing it performed, the ITa is responsible for planning, documenting, coordinating and implementing integrated system testing.  If qualified, the role of the ITa can be played by the owner or the installation contractor.
  4. An integrated system test plan is required to be developed by the ITa.  The test plan is required to include items such as the systems to be tested, documentation that individual system testing has been performed, members of the integrated system test team, a functional matrix for the integrated systems, test scenarios, test schedule and frequency of periodic integrated system testing. 
  5. Provides details on the test methods and scenarios that should be developed for use in the integrated test plan.  This section focuses on what should be in the test methods, not the actual method itself, as no two integrated FP&LSS systems may be the same.
  6. NFPA 4 provides requirements for when periodic testing is to occur.  Periodic integrated system testing is only required if some other charging document requires compliance with NFPA 4.  Periodic testing is required based on the frequency noted in the integrated test plan.
  7. For existing systems that do not have an integrated test plan, NFPA 4 requires that an integrated test plan be developed within five years of the adoption of the standard (by May 2019).  This test plan would provide the requirements for periodic integrated systems testing.  If a test plan is not developed within that time frame, integrated systems testing is required to be performed.  So, the owner is either required to develop a test plan that documents when periodic testing will occur or perform integrated systems testing, which also requires the development of a test plan.

The Future of NFPA 3 and 4
The next editions of NFPA 3 and 4 are part of the Annual 2017 revision cycle with the first set of public comments due on July 6, 2015, less than one year away.  There has been much discussion about whether or not NFPA 3 will remain a recommended practice or if it will become a standard.  At a minimum, both documents will continue to expand to provide more guidance and clarification for commissioning and integrated FP&LSS system testing. 
Doug Fisher is with Fisher Engineering, Inc. 

  1. NFPA 3, Recommended Practice for Commissioning of Fire Protection and Life Safety Systems, National Fire Protection Association, Quincy, MA, 2015.
  2. NFPA 4, Standard for Integrated Fire Protection and Life Safety System Testing, National Fire Protection Association, Quincy, MA, 2015.
  3. Hague, D.  Commissioning Fire Protection Systems, National Fire Protection Association, Quincy, MA, 2005.

Related Articles:

 

 

4th Quarter 2013 – Industrial Fire Protection – Jonathan M. Eisenberg, P.E., Rolf Jensen & Associates, Inc.
This article explains how to get started with an industrial facility project, from asking the initial questions about how the facility is laid out, to surveying the raw materials involved, to understanding the processes and conditions involved. Topics covered include codes and standards, fire suppression and detection systems, ventilation systems, electrical and power systems, and controls and interlocks. READ MORE

 

 

3rd Quarter 2013 – Fire Protection Inspection, Testing, and Maintenance and Building Fire Risk -- Francisco Joglar, Ph.D., Hughes Associates
This article describes how inspection, testing, and maintenance of fire protection can be incorporated into a building fire risk model so that such activities can be managed on a performance-based approach in specific applications. The author defines "fire risk” for the purpose of this article as a quantitative measure of the potential for realization of unwanted fire consequences. He also explains how maintenance issues factor into the risk equation. READ MORE

 


For questions concerning delivery of this eNewsletter, please contact our Customer Service Department at (216) 931-9934 or magazine.sfpe.org.

 
Copyright 2014, SFPE and Penton.